How we carry out a retrofit

A retrofit replaces the controller, not the plant. To keep this predictable, we work to a fixed process. If the software is missing, we retrieve it from the controller. You know at all times what is happening and what you will have at the end.

The process at a glance

The route depends on whether your plant's software still exists.

The steps in detail

  1. On-site survey

    We record the controller, inputs and outputs, fieldbus system, operator panels and the condition of the control cabinet, review existing circuit diagrams and talk to maintenance staff and operators. The key question is: is there still a software project or at least a program printout? If so, we go straight on to reprogramming.

    Result for youSurvey report with hardware and I/O overview and clear next steps

    Survey of a Moeller PS416
  2. Read out software

    If the software is missing, we read the program directly from the running controller or memory card. We have the right equipment for old Moeller systems. The plant can usually keep running.

    Result for youBacked-up program from the controller

    Memory card of a Moeller PS416
  3. Our speciality

    Decompiling

    This is our speciality. With our own tools we translate the read-out PLC code back into a readable program. We also solve difficult cases such as password-protected programs. This shows what the plant actually does, even if there is no longer any original project or documentation.

    Result for youReadable, commentable program as the basis for reprogramming

    Decompiled Moeller program
  4. Reprogramming and EPLAN

    The program is rebuilt in TIA Portal or Beckhoff TwinCAT: structured, cleanly documented and to current standards, with visualisation and alarm system. In parallel, we update the EPLAN drawings or create them from scratch.

    Result for youTested program, visualisation and up-to-date EPLAN

    New Siemens S7-1500 before commissioning
  5. Conversion

    During the planned shutdown, we replace the old controller with a modern Siemens or Beckhoff controller. The field wiring is retained wherever possible. This significantly shortens the conversion.

    Result for youNew controller in the existing control cabinet

    Control cabinet after conversion to S7-1500
  6. Commissioning, testing and handover

    We check every signal, commission the plant and test all functions. We then hand over the plant with program, EPLAN and documentation. You receive the new program unencrypted and without block protection: it belongs to you, and you are not tied to anyone.

    Result for youRunning, fully documented plant and unencrypted program

    New operator panel after handover

What you gain as the operator

Predictable downtime

The conversion is prepared and tested in advance. The plant is only down during the agreed time window.

Same function, new basis

The plant behaves as usual. We only implement improvements if you want them.

Spare parts for years

Current Siemens or Beckhoff hardware that your maintenance team knows and can source.

Finally documented

Program, hardware and function are properly documented after the retrofit.

Your program belongs to you

We hand over the new program unencrypted. You can change it yourself or have it changed at any time.

Project examples

Control cabinet with Moeller PS416 before the retrofit
Before
Control cabinet with Siemens S7-1500 after the retrofit
After

PS416 to S7-1500

Existing system
Moeller PS416
New
Siemens S7-1500, TIA Portal
Special feature
Field wiring reused

More about the PS416

Control cabinet with Moeller PS4 before the retrofit
Before
Control cabinet with Siemens ET 200SP after the retrofit
After

PS4 to ET 200SP

Existing system
Moeller PS4
New
ET 200SP with S7-1500 CPU
Special feature
Compact design in the existing cabinet

More about the PS4

Control cabinet with Moeller PS24 before the retrofit
Before
Control cabinet with Siemens S7-1500 after the retrofit
After

PS24 to S7-1500

Existing system
Moeller PS24
New
Siemens S7-1500
Special feature
Custom-made connector plates, conversion time reduced to a minimum

More about the PS24

Frequently asked questions

How long does a retrofit take overall?

From survey to handover usually a few weeks to a few months, depending on plant size and delivery times. The actual downtime is only a small part of this.

Who decides on the target system?

You do. We recommend a system that suits your plant standard and your maintenance team, usually Siemens S7-1500 or Beckhoff TwinCAT.

Will the function of the plant change?

No, unless you want it to. The basis is the agreed functional description. Any improvements you request are recorded separately in it.

Do you also retrofit Siemens controllers?

Yes. Migration from S7-300 and S7-400 to S7-1500 with TIA Portal is also part of our work.

Planning a retrofit?

It starts with the survey. Send us the type and photos, and we will get back to you with a proposed date.